Equinor will be forced to delay oil, gas and electrification projects in Norway if the government doesn’t improve its tax-deferral proposal, CEO
- Examples of projects that would need to be delayed are Wisting, Krafla, Peon and electrification of Hammerfest LNG plant
- NOTE: April 30,
Norway Oil Lobby Says Government Tax Measures Aren’t Good Enough
- NOTE: April 30,
- Equinor expects production startup on its Martin Linge, Njord, Bauge and Peregrino 2 projects, planned this year, to be delayed to 2021 because of challenges related to coronavirus
- Equinor can’t rule out layoffs or job cuts
- CEO says gas market is likely to rebalance faster than oil market
- EARLIER:
Equinor Abandons Production Target as Profit Plunges 63%